Most standard or bespoke construction contracts provide for interim payment during the works. If the contracting parties have failed to set out contractual terms for interim payment the Housing Grants, Construction and Regeneration Act 1996 (“Construction Act”) will imply interim payment terms into the contract via The Scheme for Construction Contracts (England and Wales) Regulations (“the Scheme”).
Essentially the regime is as follows:-
- Contractor or Subcontractor (“payee”) makes an application for payment, valuing works up to an agreed or default “due date”
- Shortly after the due date the Employer or Main Contractor (“payer”) should issue a response to the application. This is called a “payment notice” and must specify the sum the payer considers is “due” at the due date and the “basis on which that sum is calculated”
- If a payment notice has not been issued and / or if the payer decides it wants to pay less than the sum set out in the application or payment notice it can issue a “pay less notice”. This pay less notice must be issued not later than the agreed number of days before the “final date for payment”
- The final date for payment is, by default, 17 days from the due date but is usually amended to be 14 or 28 days from the due date
- This exchange of applications and notices should take place as determined by the parties or as set out in the Scheme
- If no payment notice or pay less notice is served by the payer the amount set out in the application becomes the “notified sum” due for payment. Otherwise the amount set out in the payment notice or, if served, the pay less notice, is the notified sum that the payer must pay by the final date for payment.